METHOD-RELATED CHARGES (MRC): THE COST EFFECTS WHICH RELATED TO THE CLAIMS
BY
NORAZMI BIN FADILAH
A dissertation submitted in fulfilment of the requirement for the degree of Master of Science in Quantity Surveying and
International Procurement
Kulliyyah of Architecture and Environmental Design International Islamic University Malaysia
JULY 2018
ii
ABSTRACT
In construction projects, the Bill of Quantities (BQ) is used to provide a detailed description of the total value of an item and serve as a normal payment mechanism for work procured by the related parties, such as contractors. However, the Bill of Quantities (BQ) has some essential flaws, the biggest of which being that construction costs are rarely directly proportional to the quantity. The effect of this flaw may be minimal if changes in the scope of the works are few, as the difference between the contractor‟s costs and income will remain small. The concept of Method-related Charges (MRC) will increase the change in scope that can be accommodated.
Nevertheless, friction often results when significant changes in scope or methods occur, as the contractor struggles to justify any additional entitlement and to show where his extra costs come from. This research aims to investigate the issues pertaining to the Method-related Charges (MRC). The focus of the research is on how to evaluate the cost effects of Method-related Charger (MRC) on construction and to develop measures to minimize the impact of cost related issues raised under Method- related Charges (MRC) claims. Another difficulty arises with Method-related Charges (MRC) items, which is that the Civil Engineering Standard Method of Measurement (CESMM) clause states that a Method-related Charges (MRC) does not bind the contractor to use the method defined; it is not subject to admeasurement; and is not to be increased or decreased for any change method adopted by the contractor. This research uses an explanatory paradigm approach in exploring the issue by employing a qualitative method. Data collection is comprised of interviews and document reviews that aim to investigate the issue of Method-related Charges (MRC), to evaluate the cost effects of Method-related Charges (MRC), and therefore to minimize the cost related issues in the claim of Method-related Charges (MRC). Interviews were conducted among construction practitioners and content analysis was used to analyse the data collected. Validation of the findings from this research is achieved through triangulation of interviews and document analysis. The findings from this research found that Method-related Charges (MRC) enables the contractor optionally to enter separately in the tender such non-quantity proportional charges as considered will have a significant influence on the cost of the works and for which the contractor omits to enter into Method-related Charges (MRC). The significant outcomes of this research are expected to give a new perspective on the Method-related Charges (MRC).
iii
ةصلاخ ثحبلا
في عيراشم
،ءانبلا متي مادختسا ةروتاف
تايمكلا (
BQ ) ل دنبلل يليصفتلا فصولا ةميق مييقت
، نوكتو
ةباثبم ةيلآ عفد ةيداع لمعل تم هؤارش نم لبق فارطلأا تاذ
،ةقلاعلا لثم
ينلواقلدا . عمو
،كلذ نإف نوناق
تايمكلا (
BQ ) ويدل ضعب بويعلا
،ةيساسلأا اىبركأو
نأ لاكت في ءانبلا ًاردان ام بسانتت اًيدرط
عم
ةيمكلا . دقو نوكي يرثأت اذى لللخا ًلايئض اذإ تناك تايريغتلا في
قاطن لامعلأا
،ةليلق نلأ قرفلا ينب
فيلاكت دهعتلدا
وتاداريإو ًلايئض لظيس
. ديزيس موهفم موسرلا تاذ ةلصلا ةقيرطلاب ( MRC )
يريغتلا في
قاطنلا يذلا نكيد وباعيتسا . عمو
،كلذ ثديح كاكتحلاا اًبلاغ
دنع ثودح تايريغت
ةيربك في قاطنلا
وأ
،قرطلا ثيح لضاني لواقلدا ريبرتل يأ قاقحتسا فياضإ
حاضيلإو ردصم
وفيلاكت ةيفاضلإا . فدهي
اذى ثحبلا لىإ قيقحتلا في
اياضقلا ةقلعتلدا
موسرلاب تاذ ةلصلا ةقيرطلاب ( MRC .)
و زكري ثحبلا
ىلع ةيفيك مييقت راثآ ةفلكتلا نحاوشل قرطلا
تاذ ةلصلا ( MRC )
ىلع
،ءاشنلإا عضوو
تاءارجإ
دحلل نم يرثأت اياضقلا تاذ ةلصلا فيلاكتلاب تيلا
راثت في راطإ تابلاطم موسرلا
تاذ ةلصلا ةقيرطلاب
( MRC .)
كانىو ةبوعص ىرخأ أشنت عم دونب موسرلا تاذ ةلصلا قرطلاب ( MRC )
، يىو نأ
طرش سايقلا يسدنلذا قلا
يساي سايقلل ( CESMM )
صني ىلع نأ ةنحشلا تاذ
ةلصلا ةقيرطلاب
( MRC )
لا مزلت لواقلدا مادختساب ةقيرطلا
؛ةددلمحا و لا عضيخ لوبقلل . لاو يغبني اتهدايز وأ اهضيفتخ
يلأ ةقيرط يريغت اىدمتعي لواقلدا
. مدختسي اذى
ثحبلا ةبراقم
ةيجذونم ةيحيضوت
في فاشكتسا
ةلكشلدا نم
للاخ دختسا ما ةقيرط ةيعون . و فلأتي عجم تانايبلا نم
تلاباقلدا تاعجارمو
تادنتسلدا
تيلا فدته لىإ قيقحتلا في
ةلأسم موسرلا تاذ ةلصلا قرطلاب ( MRC )،
مييقتل راثآ ةفلكتلا موسرلل
تاذ ةلصلا ةقيرطلاب ( MRC )،
لياتلابو ليلقتل تلاكشلدا ةقلعتلدا
ةفلكتلاب لىإ
دلحا نىدلأا في ةبلاطلدا
لا موسر ةقلعتلدا ةقيرطلاب ( MRC .)
دقل تيرجأ تلاباقلدا ينب
يسرامم ءانبلا تمو مادختسا ليلتح
ىوتلمحا
ليلحتل تانايبلا تيلا
تم اهعجم . ققحتي ققحتلا نم جئاتنلا نم اذى ثحبلا نم للاخ ثيلثت تلاباقلدا
ليلتحو ةقيثولا . ترفسأو جئاتن
اذى ثحبلا نأ موسرلا تاذ ةلصلا ةقيرطلاب ( MRC )
نكتد لواقلدا
ايرايتخا نم
لوخدلا لكشب
لصفنم في
ةصقانلدا لثم
موسرلا ةيبسنلا يرغ ةيمكلا امك وى حضوم
و نوكيس الذ
يرثأت يربك ىلع ةفلكت لامعلأا تيلاو
اهفذيح لواقلدا لوخدلا لىإ
موسرلا تاذ ةلصلا
ةقيرطلاب ( MRC .)
نم عقوتلدا نأ يطعت جئاتنلا ةمالذا اذلذ ثحبلا ةرظن ةديدج ىلع موسرلا تاذ
ةلصلا
ةقيرطلاب
(
MRC
.)
iv
APPROVAL PAGE
I certify that I have supervised and read this study and that in my opinion, it conforms to acceptable standards of scholarly presentation and is fully adequate, in scope and quality, as a thesis for the degree of Master of Science in Quantity Surveying and International Procurement
………..
Mohammad Saiful Nizam Mohd Suhaimi
Supervisor
I certify that I have read this study and that in my opinion it conforms to acceptable standards of scholarly presentation and is fully adequate, in scope and quality, as a thesis for the degree of Master of Science in Quantity Surveying and International Procurement
………..
Mohd Shariffuddin Ibrahim Internal Examiner
This dissertation was submitted to the Department of Quantity Surveying and is accepted as a fulfilment of the requirement for the degree of Master of Science in Quantity Surveying and International Procurement
………..
Azrin Mohd Din
Head, Department of Quantity Surveying
This dissertation was submitted to the Kulliyyah of Architecture and Environmental Design and is accepted as a fulfilment of the requirement for the degree of Master of Science in Quantity Surveying and International Procurement
………..
Abdul Razak Sapian
Dean, Kulliyyah of Architecture and Environmental Design
v
DECLARATION
I hereby declare that this dissertation is the result of my own investigations, except where otherwise stated. I also declare that it has not been previously or concurrently submitted as a whole for any other degrees at IIUM or other institutions.
Norazmi bin Fadilah
Signature ... Date ...
vi
INTERNATIONAL ISLAMIC UNIVERSITY MALAYSIA
DECLARATION OF COPYRIGHT AND AFFIRMATION OF FAIR USE OF UNPUBLISHED RESEARCH
METHOD-RELATED CHARGES (MRC): THE COST EFFECTS WHICH RELATED TO THE CLAIMS
I declare that the copyright holders of this dissertation are jointly owned by the student and IIUM.
Copyright © 2018 Norazmi bin Fadilah and International Islamic University Malaysia. All rights reserved.
No part of this unpublished research may be reproduced, stored in a retrieval system, or transmitted, in any form or by any means, electronic, mechanical, photocopying, recording or otherwise without prior written permission of the copyright holder except as provided below
1. Any material contained in or derived from this unpublished research may be used by others in their writing with due acknowledgement.
2. IIUM or its library will have the right to make and transmit copies (print or electronic) for institutional and academic purposes.
3. The IIUM library will have the right to make, store in a retrieved system and supply copies of this unpublished research if requested by other universities and research libraries.
By signing this form, I acknowledged that I have read and understand the IIUM Intellectual Property Right and Commercialization policy.
Affirmed by Norazmi bin Fadilah
……..……….. ………..
Signature Date
vii
This dissertation is dedicated to my beloved parents and my brothers and sisters and to my wife and my daughter’s Nur Qistina binti Norazmi.
viii
ACKNOWLEDGEMENTS
All praises to the almighty Allah S.W.T, the most gracious and merciful for granting me with strength, courage and passion to believe in this pursuit.
My foremost gratitude goes to my principal supervisor, Dr Mohamad Saiful Nizam Bin Mohd Suhaimi for his never-ending guidance, motivation, enthusiasm and optimism towards my MSc Quantity Surveying and International Procurement dissertation work in Kulliyah of Architecture and Environmental Design (KAED) under the Department of Quantity Surveying, International Islamic University Malaysia (IIUM).
Dr Mohamad Saiful Nizam Bin Mohd Suhaimi, he is a lifetime mentor and advisor.
To my fellow colleagues from Malaysian Polytechnic and friends whom we have been through during the ups and down, I do owe you all an appreciation. You were there when I was dejected and keep me on track. It‟s a precious friendship.
To my parents, Fadilah bin Sulaiman and Norhazah binti Nordin, brothers and sisters your positivity and support throughout my study are priceless. Thank you for your love and trust.
To my wife and my daughter (My Stardust), Nor Ashida binti Sinin and Nur Qistina binti Norazmi, your sacrifices along these years are priceless. Thank you for the support, kindness and care.
ix
TABLE OF CONTENTS
Abstract ... ii
Abstract in Arabic ... iii
Approval Page ... iv
Declaration ... v
Copyright Page ... vi
Acknowledgements ... viii
List of Tables ... xiii
List of Figures ... xiv
List of Abbreviation………..xv
CHAPTER ONE: INTRODUCTION ... 1
1.1 Background of the Study ... 1
1.2 Research Problem ... 3
1.3 Research Questions ... 5
1.4 Research Objectives... 6
1.5 Limitation of the Study ... 6
1.6 Significance of the Study ... 6
1.7 Research Network ... 7
1.8 Summary ... 8
CHAPTER TWO: LITERATURE REVIEW ... 10
2.1 Introduction... 10
2.2 Definition of Method-related Charges (MRC) ... 11
2.3 The Philosophy of Methoed-related Charges (MRC) ... 12
2.4 The Objectives of Method-related Charges (MRC) ... 13
2.5 The Purpose of Method-related Charges (MRC)... 14
2.6 The Types of Method-related Charges (MRC) ... 16
2.6.1 Time Related Charges ... 17
2.6.2 Fixed Charges ... 17
2.7 The Implication of Method-related Charges (MRC) ... 18
2.8 The Advantages and Disadvantages of Method-related Charges (MRC) ... 19
2.9 The Application of Method-related Charges (MRC)... 20
2.10 Method-related Charges (MRC) Mechanism ... 21
2.11 Claims ... 22
2.12 Definitions of Claims ... 22
2.13 Construction Claims ... 23
2.14 Types of Claims ... 25
2.14.1 Contractual Claims ... 25
2.14.2 Extra Contractual CLaims ... 26
2.14.3 Quantum Merit Claims... 26
2.14.4 Ex-Gratia Claims... 26
2.14.5 Counter Claims ... 26
2.15 Reasons for Claims ... 27
2.16 Issues of Claims ... 29
x CHAPTER TWO: LITERATURE REVIEW
2.17 Causes of Claims ... 30
2.17.1 Payment Related Claims ... 31
2.17.2 Change Claims ... 31
2.17.3 Delay Claims ... 32
2.17.4 Extra Works and Claims ... 32
2.17.5 Contractual Claims ... 33
2.17.6 Difference in Pricing & Measuring Claims ... 33
2.17.7 Different Site Condition Claims ... 33
2.17.8 Acceleration Claims ... 34
2.17.9 Damage Claims ... 34
2.17.10 Contract Termination Claims ... 34
2.18 Summary ... 35
CHAPTER THREE: RESEARCH METHODOLOGY ... 36
3.1 Introduction... 36
3.2 Definition of Research ... 36
3.3 The Types of Research (Research Design) ... 37
3.4 Steps of the Research Process ... 37
3.5 Research Methodology ... 38
3.5.1 Purpose Research ... 41
3.5.2 Qualitative Research Methodology ... 42
3.6 Research Process ... 43
3.6.1 Overview of the Research Process ... 43
3.6.2 Literature Review ... 44
3.7 Research Method ... 45
3.8 Data Collection ... 46
3.8.1 Interview ... 47
3.8.1.1 Semi-Structured Interview ... 48
3.8.1.2 Selection of Interview Method ... 49
3.8.1.3 Reason for Selecting Focused Interview (Semi- Structured) ... 50
3.8.1.4 Selecting Interview Respondents ... 51
3.8.1.5 Interview Approach ... 51
3.8.1.6 Interview Plan ... 52
3.8.1.7 Developing Interview Question ... 56
3.8.1.8 Recording Interview ... 58
3.9 Data Analysis ... 59
3.10 Report Writing ... 60
3.11 Summary ... 60
CHAPTER FOUR: DATA ANALYSIS AND FINDINGS ... 62
4.1 Introduction... 62
4.2 Analysis ... 62
4.3 Responsde Rate ... 64
4.4 Interviewee‟s Profile ... 65
4.5 Theme Generated/Data Index ... 67
4.5.1 Theme Relationship with Research Question ... 69
xi
CHAPTER FOUR: DATA ANALYSIS AND FINDINGS
4.6 Theme Exploration ... 70
4.6.1 MRC01 Expenses ... 72
4.6.2 MRC06 Bidder Own Approach ... 73
4.6.3 MRC08 Underestimated ... 74
4.6.4 MRC01 Examples ... 75
4.6.5 MRC09 Cost Sensitive ... 76
4.6.6 MRC12 Fair in Contract Management... 77
4.6.7 MRC14 Cover for Related Cost ... 78
4.6.8 MRC18 Progress Claim ... 79
4.6.9 MRC21 Justify during Tender Evaluation & Scrutinise ... 80
4.6.10 MRC22 Ask for Justification during Tender Evaluation ... 81
4.7 Triangulation of Results ... 84
4.7.1 Expenses Attributes... 85
4.7.2 Bidder Own Appraoch Attributes ... 86
4.7.3 Underestimated Attributes ... 87
4.7.4 Examples Attributes ... 88
4.7.5 Cost Sensitive Attributes ... 89
4.7.6 Fair in Contract Management Attributes ... 90
4.7.7 Cover for Related Cost Attributes ... 91
4.7.8 Progress Claim Attributes ... 92
4.7.9 Justify during Tender Evaluation & Scrutinise Attributes ... 92
4.7.10 Ask for Justification during Tender Evaluation ... 94
4.8 Summary ... 95
CHAPTER FIVE: DISCUSSION AND CONCLUSION ... 97
5.1 Introduction... 97
5.2 Conclusion from the Research Question ... 98
5.2.1What are cost related issues concerning Method-related Charges (MRC) in the Bill of Quantities (BQ) ... 99
5.2.2What are the impact/effect of the cost related issues (Claim) stemming from Method-related Charges (MRC) application in Bill of Quantities (BQ) ... 100
5.2.3What are the setback of Method-related Charges (MRC) application in Bill og Quantities (BQ) ... 101
5.2.4What are strategies to improve cost related claim corcerning Method-related Charges (MRC) ... 102
5.3 Conclusion from Objective Achievements ... 103
5.3.1Research Objective 1 ... 103
5.3.2Research Objective 2 ... 105
5.3.3Research Objective 3 ... 106
5.4 Research Limitation ... 107
5.5 Recommendation for Future Research ... 108
5.6 Summary ... 109
xii
REFERENCES ... 110
APPENDIX A: INTERVIEW QUESTION ... 115 APPENDIX B: INTERVIEW ANSWERS (EACH OF THE
PARTICIPANTS) ... 116
xiii
LIST OF TABLES
Table 3.1 Types of Research 45
Table 3.2 Variety of Qualitative Interview Types 49
Table 4.1 Participants for an Interview Session 64
Table 4.2 Interviewee‟s Profile Registry 66
Table 4.3 Themes Generated from Interview Transcripts 67
Table 4.4 Top ten (10) related Themes 68
Table 4.5 MRC01 Expenses 73
Table 4.6 MRC06 Bidder Own Approach 74
Table 4.7 MRC08 Underestimated 75
Table 4.8 MRC01 Examples 76
Table 4.9 MRC09 Cost Sensitive 77
Table 4.10 MRC12 Fair in Contract Management 78
Table 4.11 MRC14 Cover for Related Cost 79
Table 4.12 MRC18 Progress Claim 80
Table 4.13 MRC21 Justify during Tender Evaluation & Scrutinise 81
Table 4.14 MRC22 Ask for Justification during Tender Evaluation 82
xiv
LIST OF FIGURES
Figure 3.1 The Research Spiral 38
Figure 3.2 Research Flow Chart 40
Figure 3.3 Interview Plan 52
Figure 4.1 Themes Relationship with Research Objectives 83
xv
LIST OF ABBREVIATION
BQ Bills of Quantities
CESMM Civil Engineering Standard Method of Measurement CIDB Construction Industry Development Board Malaysia
MRC Method-related Charges
MyCESMM Malaysian Civil Engineering Standard Method of Measurement
PWD Public Work Department
TRC Time-related Charge
FC Fixed Charge
1
CHAPTER ONE INTRODUCTION
1.1 BACKGROUND OF THE STUDY
The construction industry is among the industry that is listed as a major contributor to the development of country's economy. The importance of the construction industry can be seen clearly through the involvement of the various industries and covers a wide range of fields. This activities include in various sectors of the construction industry (i.e.; residential, industrial, commercial, the market is, etc.) and it is not restrained to the construction phase but also the phases of pre-construction and post- construction.
According to the Construction Industry Development Board Malaysia Act 520, said the construction industry is an industry that involve in construction, installation, repair, maintenance, renewal, transfer, modify, change, dismantle or demolish (CIDB, 2004). The construction sector also comprise of planning, design, construction, changes, maintenance, repair and removal of various types of civil engineering works, structures mechanical, electrical, and other similar work. Therefore this industry includes (Ofori, 1990):
i. Companies and agencies (public and private) involved in physical construction.
ii. Provision of planning, design, coordination and management services in relation to construction.
2
The construction sector has also been recognized as one of the important sectors that can generate economic growth countries. The construction sector is also one of the sectors that are capable to stimulate economic growth when the country is facing a crisis of recession (Saidin, Zakaria and Ahmadon, 2006).
Through physically, construction industry output is expansive, overwhelming and costly and may not be exchanged or moved. It remains in one area and including the utilizing of distinctive materials and building components created by manufacturing industries. The output are comprises of development of different sorts of buildings, civil engineering which include the infrastructure works. In the construction industry, civil engineering works have a greater scope of the building.
The construction of civil engineering works has been practiced since time immemorial for the supply of infrastructure or infrastructure to other industries. The civil engineering history has begun with a defective international history such as the construction of the pyramids, canals, tunnels, highways, dams, railway networks, supply pipes water, pipes for oil and gas and other shows that the importance of the civil engineering sector in construction industry.
Therefore it is vital to create a substantial degree of standardization in the method of preparing the Bill of Quantities (BQ) and the units used in them, especially the used of Method-related Charges (MRC) by a tenderer. A tenderer could insert in the Bill of Quantities (BQ) such items for Method-related Charges (MRC) as he may decide to cover the items of work which is relating to his intended method of finishing the works. Method-related Charges (MRC) only applies in the Civil Engineering works or condition when a projects using the Malaysian Civil Engineering Standard Method of Measurement (MyCESMM) for Malaysia construction industry or Civil
3
Engineering Standard Method of Measurement (CESMM) for United Kingdom construction industry. For that reason, the used of Method of Measurement (MyCESMM) or Civil Engineering Standard Method of Measurement (CESMM) only covers a wide range of civil engineering works which include roads, railways, bridges, docks and apart from that, it is also includes the structural engineering projects such as iron work, reinforced concrete work, stone work, woodworking and brick work (Saidin, Zakarian and Ahmadon, 2006).
1.2 RESEARCH PROBLEM
Construction projects are priced using a Bill of Quantities (BQ) a detailed description of the items needed to finish the product and their costs. Bills of Quantities (BQ) are an ordinary fee instrument for work obtained beneath the traditional/sequential procurement method, where the works are significantly outlined by the employer before being put out to tender by a contractor. In any case, Bills of Quantities (BQ) have a few crucial imperfections, the greatest being that development costs are once in a while specifically corresponding to amount. The impact of this imperfection may be negligible in case changes within the scope of the works are few as the contrast between the contractor‟s costs and wage will stay little. The concept of Method- related Charges (MRC) increases the change in scope that can be accommodated.
Hence, Civil Engineering Standard Method of Measurement (CESMM) will be used as a reference for the concept of Method-related Charges (MRC). In the article
“Prowriterslanka – Civil Engineering Works” (2013), it is mentioned that it is quite difficult to analyse Method-related Charges (MRC) on tender analysis reports, due to different methods/approaches by different tenderers in general items. Therefore, it can
4
create discrepancies on the Bill of Quantities (BQ) rates especially on the pricing aspects and claims for the contractor.
Nevertheless, friction often results when significant changes in scope or methods occur, as the contractor struggles to justify any additional entitlement and to show where his extra costs come from. The situation is not helped by the lack of programming provisions in traditional conditions of contract. The concept of payment for temporary works as set out in Civil Engineering Standard Method of Measurement (CESMM) can be called into question, as it creates potential ambiguities. The engineer may choose not to itemize any temporary works under „specified requirements‟ because he leaves such works for the contractor to decide. But the contractor may maintain that the list of temporary works (such as traffic diversion, access roads and de-watering) entitles him to payment for those works on the same principles as – when an item which Civil Engineering Standard Method of Measurement (CESMM) lists for measurement is found missing – the item has to be added to a bill. To avoid this ambiguity the preamble to the bill should state that Class A items shall be measured only to the extent they are included in the contract at the time of the award; thus fixing the temporary work items measured.
Another difficulty arises with Method-related Charges (MRC) items, Civil Engineering Standard Method of Measurement (CESMM) clause state that a Method- related Charges (MRC) does not bind the contractor to use the method defined; is not subject to admeasurement; and is not to be increased or decreased for any change method adopted by the contractor (Coinloorke, 2012). But when the engineer orders a variation of some permanent work, the contractor may claim that bill rates for similar work do not apply, because the temporary works associated with that work have
5
changed but the method related item of charge remains fixed. Despite the Bills of Quantities (BQ) become so successful in saving duplication of efforts while tendering and basis for valuing works as work proceeds, in some circumstances, it is consider as difficult to analyse Method-related Charges (MRC) on the tender analysis reports. It is because of different methods/approaches by different tenderers in general items. As a result this can raise debatable issues concerning Method-related Charges (MRC).
1.3 RESEARCH QUESTION
The Research questions of this research are as follow:
• What are costs related issues concerning Method-related Charges (MRC) in the Bills of Quantities (BQ)?
• What are the impact/effect of the cost related issues (claim) stemming from Method-related Charges (MRC) application in Bills of Quantities (BQ)?
• What are the setbacks of Method-related Charges (MRC) application in Bills of Quantities (BQ)?
• What are the strategies to improve cost-related claim concerning Method- related Charges (MRC)?
6 1.4 RESEARCH OBJECTIVES
The objectives of this research are:
i. To investigate issues on the Method-related Chargers (MRC).
ii. To evaluate the cost effects of Method-related Chargers (MRC) on construction.
iii. To develop measures to minimize the cost related issues raise in the claim of Method-related Chargers (MRC).
1.5 LIMITATION OF STUDY
This study will be focusing on Method-related Charges (MRC) in the construction industry only. This report will be aimed at the construction professionals in the Malaysia construction industry. The main focus of this study is related to the Method- related Charges (MRC) in Malaysia. Therefore, Civil Engineering Standard Method of Measurement (CESMM) will be used as the references in the Malaysia construction industry especially related to the civil engineering projects.
1.6 SIGNIFICANCE OF THE STUDY
This research is mainly intended to be a reference for parties within the construction industry and others who may benefits from it. It provides information with regards to the Method-related Charges (MRC). The research eventually is expected to provide an info regarding to the cost effects of Method-related Charges (MRC) and minimizing the cost related issues in the claim of Method-related Charges (MRC).
7
In addition, it aims to enhance their knowledge pertaining to the civil engineering works. Therefore, various circumstances will be studied by looking into the cost effects and minimize the cost related to the Method-related Charges (MRC).
By understanding these, the contractors may be able to recognize the importance of Method-related Charges (MRC) and create awareness among the tenderers. These would be beneficial to the civil engineering works and creates opportunity to the contractor to manage the cost in a better way. Therefore, Method- related Charges (MRC) could be a strategy to manage by the contractor works and minimizing the cost related which affected the Method-related Charges (MRC).
1.7 RESEARCH FRAMEWORK
This research is comprised of five (5) chapters, where the brief description of each chapter is provided as follows:
a) Chapter 1 - Introduction
This chapter consists of the background of study for the research, the objective of study, limitation of study and the framework of the report.
b) Chapter 2 – Literature Review
In this chapter, the Method-related Charges (MRC) will be reviewed. Apart from that, a study of steps to be taken and challenges to be faced by the contractors towards Method-related Charges (MRC) also included in this chapter.
8 c) Chapter 3 – Research Methodology
This chapter is the primary step in initiating this research is by identifying the research issue. This was motivated by reading materials such as articles, journals and books. With the issue identified, the objective of study was then established i.e. the barriers including the challenges of using Method-related Charges (MRC) for the contractors.
d) Chapter 4 – Results and Analysis
This chapter analyses the results of the Method-related Charges (MRC), the issues on the Method-related Charges (MRC), evaluate the cost effects of Method-related Charges (MRC) and develop measures to minimize the cost related issues raise in the claims of Method-related Charges (MRC).
e) Chapter 5 – Discussion and Conclusion
This chapter summarizes and concludes the findings, as well as making recommendations for the potential further research.
1.8 SUMMARY
This chapter aims to give an overall view of the research topic. It provides the readers with the:
General view on the research topic
Brief description on the research problems
The research question
The objectives of the research
The limit of the study
9
The significance of the study
The framework of the research
The subsequent chapters will be narrowing to the general matters on the Method-related Charges (MRC). Therefore on the next chapter, the author will concentrate towards the Method-related Charges (MRC) in civil engineering works and claims regarding to the Method-related Charged (MRC).