The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

Grid Code Awareness Program:

Operating Code 2 : Outage And Other Related Planning-Transmission Outage

By :

OSMAN BIN MOHAMMED KHALID – SYSTEM OPERATION DEPARTMENT, TRANSMISSION DIVISION, TNB

20 January 2014

(2)

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

Operating Codes No.2 (OC2):

Outage and Other Related Planning

2

1. Introduction

2. Objective of OC2 3. Scope

4. ICOMS

5. Procedures

(3)

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

Introduction

3

(4)

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

Objectives of OC2

4

(5)

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

Scope

5

Introduction

(6)

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

Model Used in MGC

6

Introduction

(7)

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE) 7

ICOMS-Integrated Commissioning &

Outage Management System

Operating Codes No.2 (OC2):

Outage and Other Related Planning

(8)

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

ICOMS

8

ICOMS-Integrated Commissioning and Outage Management System

Tool to request, process, approve and produce report for outages.

Developed in-house by Cik Roslina Md Yassin

It has 3 main modules – Transmission Outage, Project Outage and Generator Outage.

Project started in 2009 and 1

st

version was rolled out on Jan 2010.

2

nd

Version rolled out on Jun 2010

3

rd

version rolled out in Sept 2011 and it was a major revamp of

ICOMS ver. 2 due to the MGC requirements.

(9)

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

Function of ICOMS

9

Introduction

ICOMS is used for the following purposes

Outage execution

Outage Review, Coordination, Rescheduling & Approval Outage Planning

and request

Outage Statistic&

Performance report summary

(10)

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

ICOMS: Login page

1 0

(11)

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE) 1 1

Introduction

PROCEDURES

Operating Codes No.2 (OC2):

Outage and Other Related Planning

(12)

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE) 1 2

Introduction

PLANNED OUTAGE

Operating Codes No.2 (OC2):

Outage and Other Related Planning

(13)

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

OC2.4.2. Grid Owner

1 3

Introduction

(14)

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

OC2.4.2.2 Grid Owner

1 4

Introduction

(15)

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

OC2.4.3 Network Operators and Distributors

1 5

Introduction

(16)

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

OC2.4.4 Directly Connected Customers

1 6

Introduction

(17)

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

OC2.4.5 Interconnected Parties

1 7

Introduction

(18)

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

OC2.4 Submission Of Planned Outage Schedules by Users - summary

1 8

Start of new FY (1

st

Sept)

Y0

30 Sept Y1 Y2-Y5

Under OC2.4.2.2, by end of Sept Grid Owner shall provide the GSO with a “Provisional Transmission Outage Schedule” which covers Year 1 on a daily

basis.

Under OC2.4.2 -2.4.4, by end of Sept Grid Owner, Network Operator & Distributor and Directly Connected

Customer shall provide the GSO with an “Indicative Transmission Outage Schedule” which covers Year 1 to

Year 5.

Note: Each year starts on the 1 st Sept.

End of FY

(31

st

Aug)

(19)

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

Planned Outage Request in ICOMS in Y0

1 9

Introduction

Today

Y0

30 Sept

1 Sept 1 Oct 11

ICOMS will be blocked for Planned Outage request for Y1 – Y5 but request for Unplanned Outage for Y0 is still allowed

Last day to key-in Planned Outage for Y1 –Y5

Start of Y1 End of Y5 First day to key-in Planned

Outage for Y1 –Y5

(20)

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE) 2 0

Operating Codes No.2 (OC2):

Outage and Other Related Planning

Operating Codes No.2 (OC2):

Outage and Other Related Planning

PLANNED OUTAGE

-Action by GSO

(21)

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

OC2.6 Planning Of Transmission Outage by GSO

2 1

Introduction

starting Y0- 1/9

Y0

ending Y0- 31/8 31 May

30 Nov

Y2-Y5 Y1

2.6.1.6 Final Tr. Sys.

Outage Plan covering Y1 to Y5 2.6.1.3 Draft of

Tr. Sys. Outage Plan for Y1-Y5

OC2.6.1 GSO will have to prepare a

(22)

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

Summary of Planned Outage Submission and Planning

2 2

Introduction

1/9

Y0

30/9 30/11 31/8

Last day to provide the GSO with a “Provisional Transmission Outage Schedule” which covers Y1 on

a daily basis by Grid Owner Last day to key in “Indicative Transmission Outage

Schedule” for Y1-Y5 by Grid Owner, Network Operator & Distributor

Note: Each year starts on the 1 st Sept.

GSO to come up with draft of Tr. Sys. Out. Plan

for Y1-Y5

GSO to come up with final of Tr. Sys. Out. Plan

for Y1-Y5 Today 31/5

Related Parties must start keying in outage

for Y1-Y5

(23)

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE) 2 3

Introduction

UNPLANNED OUTAGE - Short Duration

Unplanned Outage

Operating Codes No.2 (OC2):

Outage and Other Related Planning

(24)

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

OC2.6.2 Operational Planning Timescales for Y0 – Unplanned Outage

2 4

(25)

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

Notification For Unplanned Outage

2 5

Introduction

(26)

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

Notification For Unplanned Outage-summary

2 6

Introduction

1-Outage notification depends on plant/apparatus and outage duration.

2- Plants - BB or circuits (for 2 or more)

-other than BB or circuits (for 2 or more) 3-Outage duration - <1 day

- >1 day but <2 days

(27)

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

OC2.6.2 Notification required for Unplanned Outage

2 7

-1 Month

OC2.6.2.7 Min 14 Biz Days Notice required for outage

<1 day for equipment other

than BB & Cct (2 ccts or more)

-4 Months

Intended Outage

Date -14

Biz days OC2.6.2.7 Min 1

month notice required for outage >1 day but

<2days for equipment other

than BB & Cct (2 ccts or more) OC2.6.2.7 Min 4

months notice required for BB &

Cct (2 ccts or more)

for <2 days outage

(28)

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE) 2 8

Introduction

UNPLANNED OUTAGE - Other Than Short

Duration Unplanned Outage

Operating Codes No.2 (OC2):

Outage and Other Related Planning

(29)

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

OC2.6.2.10 Unplanned Outage- other than Short Duration Unplanned Outage

2 9

Introduction

(30)

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE) 3 0

OC2.6.2.10 Required Notification for Unplanned Outage- other than Short Duration Unplanned Outage

-1 Month

OC2.6.2.7 Min 14 Biz Days Notice required for outage

<1 day for equipment others

than BB & Cct (2 ccts or more)

-4 Months

Intended Outage

Date -14 biz

days OC2.6.2.7 Min 1

month notice required for outage >1 day but

<2days for equipment others

than BB & Cct (2 ccts or more) OC2.6.2.7 Min 4

months notice required for BB &

Cct (2 ccts or more) for <2 days outage

OC2.6.2.10 Under unavoidable circumstances – Grid Owner must notify the GSO as early as possible for

approval.

(31)

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE) 3 1

Introduction

Request For Changes Of Outages

Operating Codes No.2 (OC2):

Outage and Other Related Planning

(32)

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

OC2.6.2.2- Request for changes of outages

(33)

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

OC2.6.2.2- Request for changes of outages

3 3

Introduction

Y0 No change of outages are

allowed by Users

Users can request to change the outage by

writing in to GSO

7 weeks

(34)

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE) 3 4

Introduction

Programming Phase

Operating Codes No.2 (OC2):

Outage and Other Related Planning

(35)

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

OC2.7 Programming Phase

3 5

Introduction

OC2.7.1 Outage Report

(36)

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

OC2.7 Programming Phase…cont

3 6

Introduction

OC2.7.4 Outage Confirmation

(37)

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

OC2.7 Programming Phase-Summary

3 7

Introduction

>Wk -2 Day

ahead

OC2.7.5 7 weeks Provisional outage program by 1700 hrs (starting from Wk2 to wk8)

Wk 1 Wk8 OC2.7.4 Users

submit notification on

confirmation of outages

OC2.7.5 firmed Day ahead and week ahead outage program

by 1700 hrs

Wk 0

(Friday) Wk7

OC2.7.1 8-weeks outage program

(38)

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE) 3 8

Introduction

Live Apparatus Working

Operating Codes No.2 (OC2):

Outage and Other Related Planning

(39)

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

OC2.8.1 Scheduled Live Apparatus Working

3 9

Introduction

(40)

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

OC2.8.1 Scheduled Live Apparatus Working…cont

4 0

Last day to notify GSO for all Live Work to be done in

March

Intended live Maintenance Date

1 month

31 Jan 1 March

(41)

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

OC2.8.2 Unplanned Live Apparatus Working

4 1

Introduction

(42)

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

OC2.8.3 Live Apparatus Working at the request of the GSO

4 2

Introduction

(43)

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)

THANK YOU

Rujukan

DOKUMEN BERKAITAN

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE).. Grid Code Awareness Program Operating Code

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE).. Malaysian

(iii) MS 1979:2007, Electrical Installations of Buildings - Code of Practice sebagai garispanduan pemasangan di pepasangan elektrik dalam industri bekalan elektrik di

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE)1.

The information which the Single Buyer, and GSO shall use in assessing weekly or daily, as appropriate, which CDGU to Dispatch will be the Availability Notice, the Merit Order as

Sabah dan Labuan Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE).. Schedule and

• By 1000 hours each Business Day, each Generator shall provide the GSO in writing with a best estimate of Dispatch Unit inflexibility , or CDGU unavailability due to a

The Malaysian Grid Code Awareness Programme Funded by Akaun Amanah Industri Bekalan Elektrik (AAIBE) 2.. SDC2: Control, Scheduling